Capacity 1500 m3/day
Owner The Institution Of The Red Sea Reconstruction
Main Contractor ARAB CONTRACTORS, Red Sea Branch
Sub-Contractor  
Client ARAB CONTRACTORS, Red Sea Branch


Halaieb  sea water desalination plant is located in south Egypt. Halaieb sea water reverse osmosis desalination plantdesignedto work by using PX as an energy recovery. It consists of one train with capacity 1500 m3/day.

Water Treatment consultant office (WTCO) use the latest technologies in desalination process to accomplish

  • Stability, Durability and reliability of operation under different conditions to insure the product water quality and quantity.
  • Product water quality that match standard limits/Codes.
  • Reduction CAPEX without affecting technical specifications and product water quality.
  • Reduction OPEX without affecting technical specifications and product water quality.
  • Insure suitable area for operation and maintenance without any obstacles.

Water Treatment Consultant Office (WTCO) is unique by offering our designs and calculation of process in desalination plants in 3D drawing which facilitate the installation and operating of plants and manage us to establish plants without problems.

In Halaieb seawater desalination plant our responsibility is :-

  • Process Design.
  • Substation Design.
  • Sites general arrangement.
  • Planning and preparation working drawings and bills of quantities for electromechanical works.
  • Tender documents preparation.
  • Technical evaluation.
  • Supervising the erection.
  • Commissioning.and start up.

El Shiekh Zwaied

El Shiekh Zwaied

Capacity 5000 m3/day
Owner National Organization For Potable water & Sanitary Drainage
Main Contractor KAHA Company for Chemical Industries
Sub-Contractor  OVIVO AQUA AUSTRIA
Client OVIVO AQUA AUSTRIA


El Shiekh Zwaied sea water Reverse Osmosis desalination plant designed to be operate by using Turbo charger as an energy recovery.

In El Shiekh Zwaied Seawater desalination plant our responsibility is:-

  • Supervision of erection
  • Supervision of commissioning and start up
  • Training

إتصل بنا

  • 8 سمير عبد الرؤوف متفرع من مكرم عبيد - الدور الرابع - شقة 6 - القاهرة - مصر
  • تليفون: (+202)24116177  (+202)26701268
  • موبيل: (+202)01128670000 / (+202)01100990868
  • فاكس: (+202)24116177
  • إميل: عنوان البريد الإلكتروني هذا محمي من روبوتات السبام. يجب عليك تفعيل الجافاسكربت لرؤيته.

أرسل لنا رسالة

  Mail is not sent.   Your email has been sent.
We use cookies to improve our website. By continuing to use this website, you are giving consent to cookies being used. Cookie policy. I accept cookies from this site. Agree